SERVICE AREA · BURNABY, BC

Traffic Control Plans in Burnaby, BC

Burnaby mandates an engineer seal on all Category 2 and 3 plans. Plan for it. Don't discover it after submission.


The City of Burnaby issues a Traffic Control Permit through the Engineering Department. The standard review lead time is 10 business days. Minimum insurance is $5,000,000 CGL naming the City of Burnaby as additional insured.


Burnaby is one of the strictest municipalities in BC for engineer-seal requirements. An engineer seal is required on all Category 2 and 3 plans, not just Category 3, and not just at the reviewer's discretion. If your project in Burnaby is Category 2 or higher, the plan must have a P.Eng seal before the permit office will accept it. BPB includes P.Eng coordination in the quote for all Burnaby Category 2 and 3 plans.


Arterial corridors have peak-hour restrictions. Multi-phase projects require a phasing plan review alongside the TCP. We account for both in the plan preparation and flag any additional requirements during the quote.

QUICK REFERENCE


PERMIT TYPE
Traffic Control Permit


ISSUING BODY
City of Burnaby, Engineering Department


INSURANCE MIN
$5,000,000 CGL + additional insured


LEAD TIME
10 business days


ENGINEER SEAL
Required for Category 2 and 3, no exceptions


MULTI-PHASE
Phasing plan review required


GOVERNING BYLAW
Burnaby Traffic Bylaw No. 12964

Engineer seal required for Category 2 and 3, no exceptions

Burnaby mandates engineer review on all non-trivial plans. This applies to Category 2 as well as Category 3. BPB includes P.Eng coordination in the quote for all Burnaby Category 2 and 3 plans. It is never an afterthought.

What We Handle in Burnaby

Traffic control plans

Category 1, 2, and 3. Built to BC TMM 2020 and Burnaby requirements. P.Eng seal included for Category 2 and 3.

Traffic Control Permit applications

Application preparation and submission to Burnaby Engineering. Insurance verification and follow-up through approval.

Risk assessments

WorkSafeBC OHSR 18.3.1-compliant. Standalone or bundled with TCP.

Engineer review coordination

P.Eng review for all Category 2 and 3 plans. Coordinated by BPB, no separate procurement. Timed to your permit window.
TOOL

Jurisdiction Requirements

Select a municipality to see permit type, insurance requirements, lead times, and engineer-seal rules.


Burnaby

Permit type Traffic Control Permit
Issuing body City of Burnaby, Engineering Department
Minimum insurance $5,000,000 CGL naming City of Burnaby as additional insured
Review lead time 10 business days
Engineer seal Required for Category 2 and 3. Burnaby mandates engineer seal on all non-trivial plans
Timing notes Arterial corridors have peak-hour restrictions; multi-phase projects require phasing plan review
Governing bylaw Burnaby Traffic Bylaw No. 12964
Requirements confirmed at time of research. Confirm current standards with the issuing office before submitting.

Project in Burnaby? Let's confirm the category and engineer requirement upfront.