PRICING
Published Rates. No Surprises.
Traffic control plans are priced by category. Published starting prices for all three categories, no quote required to find out what a plan costs.
| Category | Typical Profile | Starting Price |
|---|---|---|
| 1 | Shoulder closure or single lane, low-speed road, single day, no staging | $175 |
| 2 | Multi-day, collector or arterial road, moderate speed, or two lanes affected | $225 |
| 3 | High-speed road, multi-phase staging, complex intersections, or extended duration | $325 |
Rush (24-hour turnaround): +50%
Revisions: Included until permit-ready
Engineer P.Eng review (when required): Quoted per project
Road use permit coordination: Quoted per project
How Categories Work
The category is determined by four factors: the number of lanes affected, the posted speed limit of the road, the duration of the closure, and whether the work involves multiple phases or stages. Higher complexity in any factor pushes toward a higher category.
The category is confirmed after we review your project details, not estimated by a bot. The price you see above is the starting price for each category. Most projects within a category are straightforward and land at the starting price. Complex projects within a category may be quoted above it.
You receive a confirmed category and price before any work begins. No surprises later.
Engineer Review & Sealing
Category 3 plans typically require a P.Eng seal, as do Category 2 and 3 plans in Burnaby. When engineering approval is required, we coordinate the review and sealing process. Pricing varies by project complexity, with costs and timelines provided upfront.
TOOL
Category Assessment
Four factors set your category. Send these details with your quote request and we confirm the category, starting price, and engineer-review requirement within one business day.
| Factor | Options |
|---|---|
| Lanes affected | Shoulder or boulevard only · One travel lane · Two or more travel lanes |
| Posted speed limit | 50 km/h or less · 60–70 km/h · 80 km/h or higher |
| Duration | Single day · 2–7 days · More than one week |
| Staging | Single stage · Multi-stage or phased |
| Municipality | Engineer-seal rules vary: Burnaby and Vancouver require a seal for Category 2 and 3 |
Not sure which options apply? Send what you have and we'll assess it.